In our last post, we talked about Transportation Scheduling in SAP. If you missed it, you can click here to read it.

Today, I’ll walk through how the system behaves when an unloading point calendar is assigned to the ship-to party with transportation scheduling enabled.

Note:

The example below uses SAP AFS, but the same logic applies to other SAP versions as well.

When there is no calendar assigned to the ship to party

When no Unloading Point Calendar is assigned to the ship-to party, outbound scheduling determines the confirmed delivery date in the sales order based solely on the lead time maintained in the route.

See below example:

Customer “3604200010” has no calendar assigned.

 

  • Order creation date: 17/11/2011 (Thursday)
  • Requested delivery date: 17/11/2011
  • Based on the configuration system should determine the route “360010” for this customer.
  • Lead time defined in the route – 2 days

Therefore, system should determine the confirmed delivery date as 19/11/2011 (Saturday) for the sales order.

See below for the system behavior for confirmed delivery date calculation for this customer.

System automatically set the confirmed delivery date to 19/11/2011 based on the lead time defined in the route. (Sales order – 8716609)

 

When there is a calendar assigned to the ship to party

Let’s assign a calendar which has only Friday as a working day. Calendar ZF has only Friday as working day.

 

When I assign this calendar to the ship to party, outbound scheduling can determine only Friday’s as confirmed delivery date. Therefore system should not determine 19/11/2011 as the confirmed delivery date, but 25/11/2011.

 

Assign calendar to the ship to party

Assign calendar “ZF” to the customer “3604200010”.

 

Confirmed delivery date calculation based on the customer calendar

Now let’s create a sales document for the customer. Still system determines the route “360010” which has 2 days lead time.

Though the requested delivery date is 17/11/2011, based on the customer calendar, system first moves the confirmed delivery date to the next possible Friday which is 18/11/2011. Therefore, you get below message.

Now due to outbound scheduling, system determines that 18/11/2011 is also not possible as lead time of the route “360010” is 2 days, which is 19/11/2011. Still 19/11/2011 cannot be determined as customer calendar is accepting only Fridays. Therefore, system moves the confirmed delivery date to next possible Friday which is 25/11/2011. (Sales order – 8716610)

You will not be able to change the confirmed delivery date manually back to 18/11/2011. Finally, you will see the confirmed delivery date as 25/11/2011 in the sales order. (See below)

 

Disclaimer

This article is done based on my research and readings, unless otherwise stated. The views expressed are my own and not of anyone else.

Author accepts no liability for the content of the articles in this website or for the consequences of any actions taken on the basis of the information provided. Using this information is at the users own discretion and responsibility.

Leave a Reply

Your email address will not be published. Required fields are marked *